Second-floor structural works
Sample project · Denpasar
07:30–16:30 WITA
Sunny12 workers
Site photos
10:15
3 more photos
Column reinforcement in zone B is complete. Beam formwork has started and continues tomorrow morning.
Progress
46%
Issues: The steel delivery arrived two hours late. Reinforcement in zone C moved to the afternoon.